# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 92% complete, FM 78, Bexar County ($21,679,814, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Rpv Construction, LLC (2.34%); Trp Construction Group, LLC (1.92%); Mb Prime LLC (4.63%); Flasher Equipment Company (0.24%); Greyco Construction, LLC (3.64%); Mobile Enterprises, INC. (1.56%); D&G Energy Corporation (1.11%); Buyers Barricades, INC. (0.14%) |
| Progress | 91.59% complete, 98.81% of time used |
| Amount | $21,679,814 revised (original $21,789,871) |
| Change orders | $-110,057 |
| Paid to date | $19,857,038 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 78, IH 410 to SL 1604, Bexar County, San Antonio District |
| Let / began | 2025-02-06 / 2025-07-21 |
| Latest estimate | 2026-10-06 |
| Contract number | 2253001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.