# Texas Materials Group, INC.: TxDOT widen freeway contract 88% complete, US 281, Blanco County ($12,929,540, 9 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Mpb, INC. (0%); Eggemeyer Land Clearing, LLC (0%); Buyers Barricades Austin, LLC (0%); D. I. J. Construction, INC. (0%); J. H. Oden Contracting Company (0%); The Levy Company, INC. (0%); Centerline Technologies, LLC (0.38%); Greyco Construction, LLC (0%); A K Fuquay Construction (0%) |
| Progress | 88.22% complete, 79.95% of time used |
| Amount | $12,929,540 revised (original $11,189,111) |
| Change orders | $1,474,126 |
| Paid to date | $11,171,356 |
| Work | Widen Freeway |
| Location | US 281, BURNET COUNTY LINE to 0.25 MI N OF RM 962, Blanco County, Austin District |
| Let / began | 2024-03-06 / 2024-08-20 |
| Latest estimate | 2026-10-05 |
| Contract number | 3243206 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.