# Texas Materials Group, INC.: TxDOT overlay contract 97% complete, SH 225, Harris County ($22,090,347, 10 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Kingz Industrial LLC (4.2%); Lonestar Traffic Safety, LLC (0.11%); Mc2 Civil, LLC (10.29%); Traffic Signs & Lines, LLC (2.83%); Dustrol, INC. (2.87%); A.J.J.A . Trucking, INC. (1.94%); Surface Preparation Technologies, LLC (0.09%); Batterson, LLP (2.33%); Deco Contractors, INC. (1.48%); Trp Construction Group, LLC (0.03%) |
| Progress | 97.09% complete, 210.87% of time used |
| Amount | $22,090,347 revised (original $21,982,369) |
| Change orders | $72,972 |
| Paid to date | $21,412,763 |
| Work | Overlay |
| Location | SH 225, IH 610 E to W OF S RICHEY, Harris County, Houston District |
| Let / began | 2025-03-04 / 2025-06-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 3253002 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.