# Texas Materials Group, INC.: TxDOT miscellaneous construction contract 27% complete, SH 358, Nueces County ($58,654,086, 10 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Soil Tech Advance INC. (0.34%); Camacho Demolition, LLC (0.06%); Highway Barricades And Services, LLC (1.22%); Primate Construction, LP (0.06%); Jb Pinnacle Group, LLC (3.25%); Superior Grouting Services, INC. (0.07%); The Levy Company, INC. (5.83%); Performance Equipment Service (0.37%); D & C Concrete Cutting, INC. (0.11%); Capital Pumping, LP (0.01%) |
| Progress | 26.74% complete, 36.26% of time used |
| Amount | $58,654,086 revised (original $57,997,939) |
| Change orders | $656,147 |
| Paid to date | $15,681,440 |
| Work | Miscellaneous Construction |
| Location | SH 358, NILE DRIVE to STAPLES STREET, Nueces County, Corpus Christi District |
| Let / began | 2024-04-04 / 2025-03-31 |
| Latest estimate | 2026-10-02 |
| Contract number | 4243002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.