# Texas Materials Group, INC.: TxDOT widen non-freeway contract 51% complete, FM 1130, Orange County ($3,966,810, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | 4e Tree Worx LLC (2.38%); Trp Construction Group, LLC (2.05%); Structural Integrity Group LLC (0.27%); J & M Contracting, Company (16.75%); American Remediation Options, INC. (7.48%) |
| Progress | 50.96% complete, 44.25% of time used |
| Amount | $3,966,810 revised (original $3,916,262) |
| Change orders | $50,549 |
| Paid to date | $2,021,560 |
| Work | Widen Non-Freeway |
| Location | FM 1130, FM 1136, EAST to 4.24 MILES, Orange County, Beaumont District |
| Let / began | 2025-04-04 / 2025-08-04 |
| Latest estimate | 2026-10-01 |
| Contract number | 4253220 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.