# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 45% complete, US 175, Dallas County ($29,529,856, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Fortson Contracting, INC. (2.38%); Gibson & Associates, INC. (10.73%); Texas Traffic And Barricade, LLC (0.3%); Dustrol, INC. (3%); Jr West Texas Concrete LLC (3.35%); O. Trevino Construction, LLC (9.52%); Linear Traffic Markings LLC (1.32%); S&S Bridge Painting (1.73%); Ibctx, LLC (1.85%); J. H. Oden Contracting Company (0.68%); Act Saw Cutting & Removal (1.2%); Macias Specialty Contracting LLC (3.14%); Brenda Price Trucking, INC. (0.47%); (Inactive)site Barricades (0.3%) |
| Progress | 45.12% complete, 81.28% of time used |
| Amount | $29,529,856 revised (original $28,303,656) |
| Change orders | $-52,300 |
| Paid to date | $12,747,095 |
| Work | Rehabilitation Of Existing Road |
| Location | US 175, BEXAR STREET to IH 20, Dallas County, Dallas District |
| Let / began | 2024-05-02 / 2024-10-14 |
| Latest estimate | 2026-10-02 |
| Contract number | 5243007 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.