# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 49% complete, SH 36, Austin County ($6,480,610, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Stripe Lines, INC. (2.6%); Cen Tex Hydroseed, INC. (0.36%) |
| Progress | 48.94% complete, 87.86% of time used |
| Amount | $6,480,610 revised (original $6,157,668) |
| Paid to date | $3,013,661 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 36, SH 159 W to SH 159 E, Austin County, Yoakum District |
| Let / began | 2025-05-02 / 2026-02-10 |
| Latest estimate | 2026-10-05 |
| Contract number | 5253209 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.