# Texas Materials Group, INC.: TxDOT miscellaneous construction contract 100%+ complete, IH 35, Comal County ($6,800,363, 10 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Flasher Equipment Company (0.35%); Trp Construction Group, LLC (1.25%); F & W Electrical Contractors, INC. (8.67%); Roadway Specialties, INC. (0.19%); Capital Excavation Company (4.53%); G 6 Construction, INC. (9.87%); Scott Derr Painting Co, LLC (0.03%); Slick City Contractors (0.09%); 4e Tree Worx LLC (0%); Farr Foundation, INC. (3.56%) |
| Progress | 106.22% complete, 133.65% of time used |
| Amount | $6,800,363 revised (original $5,145,675) |
| Change orders | $1,654,688 |
| Paid to date | $7,223,158 |
| Work | Miscellaneous Construction |
| Location | IH 35, AT FM 725 to ., Comal County, San Antonio District |
| Let / began | 2021-06-04 / 2022-01-10 |
| Latest estimate | 2026-10-05 |
| Contract number | 6213209 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.