# Texas Materials Group, INC.: TxDOT bridge replacement contract 57% complete, FM 646, Galveston County ($16,646,178, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Aggregate Technologies, INC. (0.05%); Third Coast Services LLC (0.04%); Industrial Fabrics, INC. (0.32%); Superior Grouting Services, INC. (0.02%); Primate Construction, LP (0.05%); Green Sage Services LLC (3.14%); Hb Farmer Foundation, LLC (1.31%); Traffic Signs & Lines, LLC (2.39%) |
| Progress | 57.32% complete, 40.44% of time used |
| Amount | $16,646,178 revised (original $16,604,494) |
| Change orders | $-1,401,116 |
| Paid to date | $8,713,931 |
| Work | Bridge Replacement |
| Location | FM 646, SH 6 to FM 2004, Galveston County, Houston District |
| Let / began | 2023-06-27 / 2024-03-22 |
| Latest estimate | 2026-09-30 |
| Contract number | 6233411 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.