# Texas Materials Group, INC.: TxDOT overlay contract 100%+ complete, BS 21P, Nacogdoches County ($11,088,431, 7 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Drewery Construction Company, Incorporated (11.42%); Striping Technology, L.P. (2.22%); Dustrol, INC. (5.93%); Panola Sign & Barricade, INC. (0.37%); Railpros Field Services, INC. (0.09%); Leland & Bradlee Construction, INC. (6.04%); Prolots LLC (5.15%) |
| Progress | 105.61% complete, 113.04% of time used |
| Amount | $11,088,431 revised (original $10,814,631) |
| Paid to date | $11,421,166 |
| Work | Overlay |
| Location | BS 21P, US 59 to 0.338 MI W OF FM 225, Nacogdoches County, Lufkin District |
| Let / began | 2024-06-06 / 2025-02-03 |
| Latest estimate | 2026-10-05 |
| Contract number | 6243217 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.