# Texas Materials Group, INC.: TxDOT restoration contract 100%+ complete, FM 1414, Newton County ($3,964,290, 8 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | American Remediation Options, INC. (2.41%); Interstate Barricades & Markings, INC. (0.27%); J & M Contracting, Company (6.5%); Leland & Bradlee Construction, INC. (2.81%); Texop Construction (0.89%); Trp Construction Group, LLC (2.34%); Universal Land Clearing, LLC (10.09%); Ace Contractors, INC. (0.15%) |
| Progress | 104.3% complete, 99.2% of time used |
| Amount | $3,964,290 revised (original $3,448,292) |
| Change orders | $515,998 |
| Paid to date | $4,134,682 |
| Work | Restoration |
| Location | FM 1414, SH 63, SOUTH to FM 2991, Newton County, Beaumont District |
| Let / began | 2024-07-09 / 2025-01-06 |
| Latest estimate | 2026-10-01 |
| Contract number | 7243010 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.