# Texas Materials Group, INC.: TxDOT restoration contract 76% complete, US 87, Gillespie County ($9,622,971, 8 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | 4e Tree Worx LLC (1.13%); Buyers Barricades Austin, LLC (0.29%); Southwest Road & Safety Contractors, LTD. (1.99%); D. I. J. Construction, INC. (11.91%); Performance Equipment Service (4.55%); A K Fuquay Construction (0.05%); Mpb, INC. (0.1%); Allen Keller Company (0%) |
| Progress | 75.93% complete, 48.85% of time used |
| Amount | $9,622,971 revised (original $9,157,488) |
| Change orders | $157,680 |
| Paid to date | $7,072,941 |
| Work | Restoration |
| Location | US 87, RM 648 to US 290, Gillespie County, Austin District |
| Let / began | 2025-07-02 / 2026-05-11 |
| Latest estimate | 2026-10-05 |
| Contract number | 7253208 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.