# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 97% complete, FM 975, Burleson County ($6,044,710, 9 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Gregory Pile Driving, INC. (0.37%); Brock Construction, LLC (0.3%); Murray Construction (0.54%); Stripe Lines, INC. (0.21%); Traffic Signs & Lines, LLC (1.55%); Scr Civil Construction, LLC (2.47%); Hemphill Wbe Pile Driving Co. (0.37%); Norman Construction Services, LLC (5.32%); Cen Tex Hydroseed, INC. (1.95%) |
| Progress | 96.51% complete, 93.09% of time used |
| Amount | $6,044,710 revised (original $5,263,760) |
| Change orders | $762,660 |
| Paid to date | $5,816,365 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 975, SH 21 to UPRR OVERPASS, Burleson County, Bryan District |
| Let / began | 2023-08-03 / 2024-01-25 |
| Latest estimate | 2026-09-29 |
| Contract number | 8233228 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.