# Texas Materials Group, INC.: TxDOT hazard elimination & safety contract 100% complete, US 287, Ellis County ($10,989,299, 7 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Traffic Highway Maintenance, LLC (0%); Linear Traffic Markings LLC (0%); Southwest Road & Safety Contractors, LTD. (0%); Dustrol, INC. (0%); Texas Environmental Management - San Antonio, INC. (0%); Jr West Texas Concrete LLC (0%); 2h Striping, Limited Liability Company (0%) |
| Progress | 99.88% complete, 161.9% of time used |
| Amount | $10,989,299 revised (original $10,720,299) |
| Paid to date | $10,707,473 |
| Work | Hazard Elimination & Safety |
| Location | US 287, WALNUT GROVE to BUS 287R, Ellis County, Dallas District |
| Let / began | 2024-08-01 / 2025-03-10 |
| Latest estimate | 2026-10-05 |
| Contract number | 8243005 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.