# Texas Materials Group, INC.: TxDOT overlay contract 100%+ complete, IH 37, Live Oak County ($15,031,592, 10 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Southwest Road & Safety Contractors, LTD. (3.12%); 4e Tree Worx LLC (0.57%); Relmco, INC. (27.72%); Highway Barricades And Services, LLC (3.68%); Interstate Barricades & Markings, INC. (0.24%); Professional Traffic Control LLC (0.27%); Scott Derr Painting Co, LLC (0.79%); A K Fuquay Construction (0.08%); Mpb, INC. (0.77%); Texas Cutting & Coring, LP (0.18%) |
| Progress | 102.17% complete, 104.32% of time used |
| Amount | $15,031,592 revised (original $14,385,828) |
| Change orders | $645,764 |
| Paid to date | $15,357,874 |
| Work | Overlay |
| Location | IH 37, 3.9 MILES NORTH OF SH 72 to 0.5 MILES NORTH OF US 59, Live Oak County, Corpus Christi District |
| Let / began | 2024-08-02 / 2024-12-02 |
| Latest estimate | 2026-10-02 |
| Contract number | 8243207 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.