# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 32% complete, IH 45, Dallas County ($19,175,439, 11 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Ibctx, LLC (0.58%); Cherokee Services (0.05%); Fortson Contracting, INC. (1.37%); Dustrol, INC. (2.75%); Jr West Texas Concrete LLC (9.27%); J. H. Oden Contracting Company (4.25%); Stripe-A-Zone, LLC (1.83%); Civil Tree Solutions, LLC (0.59%); Area Wide Protective, INC. (0.16%); Silver Creek Construction, INC. (7.89%); (Inactive)site Barricades (0.2%) |
| Progress | 32.02% complete, 31.06% of time used |
| Amount | $19,175,439 revised (original $18,231,669) |
| Change orders | $18,270 |
| Paid to date | $5,844,174 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 45, AT COTTONWOOD ROAD to ., Dallas County, Dallas District |
| Let / began | 2025-09-05 / 2025-12-08 |
| Latest estimate | 2026-10-02 |
| Contract number | 9253203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.