# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 20% complete, FM 893, San Patricio County ($12,243,593, 3 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | D & C Fence Co., INC. (0.14%); *austin Traffic Signal Construction Co., INC. (1.89%); Highway Barricades And Services, LLC (0.59%) |
| Progress | 19.5% complete, 3.02% of time used |
| Amount | $12,243,593 revised (original $11,945,410) |
| Change orders | $298,183 |
| Paid to date | $2,388,002 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 893, CR 3685 (STARK RD) to .2 MI W OF CR 79 (GUM HOLLOW), San Patricio County, Corpus Christi District |
| Let / began | 2025-09-05 / 2026-01-12 |
| Latest estimate | 2026-10-02 |
| Contract number | 9253206 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.