# Texas Steel Industrial Placing, LLC: TxDOT bridge replacement contract 99% complete, CR, Lavaca County ($1,571,424, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Texas Steel Industrial Placing, LLC |
| Subcontractors | M & D Foundation Drilling Industries, INC. (9.57%); Doran Steel, INC. (0%); Environmental Safety Services, INC. (0.21%); Bobcat Services, INC. (6.51%); Houston Sawing & Drilling (0.28%) |
| Progress | 99.44% complete, 52.78% of time used |
| Amount | $1,571,424 revised (original $1,508,380) |
| Change orders | $39,240 |
| Paid to date | $1,538,901 |
| Work | Bridge Replacement |
| Location | CR, CR 177 AT BOGGY CREEK to STR# AA01-32-001, Lavaca County, Yoakum District |
| Let / began | 2025-09-04 / 2026-01-12 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253029 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.