# Third Coast Services LLC: TxDOT traffic signal contract 89% complete, SL 521, Jackson County ($2,644,035, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Third Coast Services LLC |
| Subcontractors | Trp Construction Group, LLC (3.01%); Menade, INC. (9.57%) |
| Progress | 89.13% complete, 101.72% of time used |
| Amount | $2,644,035 revised (original $2,617,632) |
| Paid to date | $2,333,100 |
| Work | Traffic Signal |
| Location | SL 521, @ PUMPHREY ST to ., Jackson County, Yoakum District |
| Let / began | 2024-11-06 / 2025-07-14 |
| Latest estimate | 2026-10-05 |
| Contract number | 11243018 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.