# Thk Construction LLC: TxDOT hazard elimination & safety contract 90% complete, BU 271B, Lamar County ($2,326,498, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Thk Construction LLC |
| Subcontractors | Catocon, INC. (2.72%); Diamond Elite Barricades, LLC (0.75%); Area Wide Protective, INC. (0.64%); A. E. Moore Construction, INC. (2.93%); Southwest Environment Services LLC (2.85%) |
| Progress | 89.88% complete, 95.74% of time used |
| Amount | $2,326,498 revised (original $2,222,429) |
| Change orders | $27,004 |
| Paid to date | $2,021,887 |
| Work | Hazard Elimination & Safety |
| Location | BU 271B, BU 271B FROM 18TH SE TO 34TH SE, Lamar County, Paris District |
| Let / began | 2024-11-06 / 2025-01-15 |
| Latest estimate | 2026-10-05 |
| Contract number | 11243022 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.