# Thk Construction LLC: TxDOT maintenance contract 80% complete, Various, Wichita County ($3,663,021, 1 sub)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Thk Construction LLC |
| Subcontractors | S & S Bridge Painting, INC. (4.79%) |
| Progress | 79.58% complete, 129.09% of time used |
| Amount | $3,663,021 revised (original $3,651,021) |
| Paid to date | $2,905,569 |
| Work | Maintenance |
| Location | Various, VARIOUS LOCATIONS to IN THE WICHITA FALLS DISTRICT, Wichita County, Wichita Falls District |
| Let / began | 2025-02-07 / 2025-07-07 |
| Latest estimate | 2026-10-02 |
| Contract number | 2253216 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.