# Thk Construction LLC: TxDOT bridge replacement contract 95% complete, SH 7, Nacogdoches County ($6,252,911, 12 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Thk Construction LLC |
| Subcontractors | Toro Bravo Construction, LLC (0.03%); Cap River LLC (1.18%); Diamond Elite Barricades, LLC (0.3%); Hodges And Son Construction Company, INC. (4.34%); Isaacs Construction Services LLC (1.26%); True Roads Construction LLC (12.8%); Kiteco Property Solutions INC. (0.59%); Morris County Contractors, L.L.C. (1.39%); Southwest Environment Services LLC (0.11%); Striping Technology, L.P. (0.98%); Third Coast Services LLC (0.69%); R & G Construction, LLC (10.96%) |
| Progress | 94.76% complete, 50.88% of time used |
| Amount | $6,252,911 revised (original $6,230,927) |
| Change orders | $17,984 |
| Paid to date | $5,921,683 |
| Work | Bridge Replacement |
| Location | SH 7, AT MORRAL CREEK to ., Nacogdoches County, Lufkin District |
| Let / began | 2025-05-01 / 2025-09-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 5253021 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.