# Thk Construction LLC: TxDOT bridge replacement contract 98% complete, CR, Cooke County ($2,475,522, 6 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Thk Construction LLC |
| Subcontractors | Dallas Lite And Barricade, INC. (0.78%); Hodges And Son Construction Company, INC. (9.01%); Morris County Contractors, L.L.C. (5.47%); Peachtree Construction, LTD. (1.99%); Toro Bravo Construction, LLC (0.06%); Wolfe Construction Group, Incorporated (0.93%) |
| Progress | 97.54% complete, 90.05% of time used |
| Amount | $2,475,522 revised (original $2,437,821) |
| Paid to date | $2,377,926 |
| Work | Bridge Replacement |
| Location | CR, CR258/SIGN CR 341 AT DRAW to ., Cooke County, Wichita Falls District |
| Let / began | 2025-07-01 / 2025-11-10 |
| Latest estimate | 2026-10-01 |
| Contract number | 7253013 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.