# Thk Construction LLC: TxDOT hazard elimination & safety contract 92% complete, SH 154, Delta County ($2,464,629, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Thk Construction LLC |
| Subcontractors | Texop Construction (0.65%); Trp Construction Group, LLC (0.97%); J. H. Oden Contracting Company (1.21%); Morris County Contractors, L.L.C. (5.14%); Peachtree Construction, LTD. (7.8%); Diamond Elite Barricades, LLC (0.44%) |
| Progress | 92.13% complete, 94% of time used |
| Amount | $2,464,629 revised (original $2,292,342) |
| Change orders | $92,879 |
| Paid to date | $2,197,407 |
| Work | Hazard Elimination & Safety |
| Location | SH 154, SH 154 FROM SH 19 TO BU 24, Delta County, Paris District |
| Let / began | 2024-09-05 / 2024-11-15 |
| Latest estimate | 2026-10-05 |
| Contract number | 9243030 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.