# Thk Construction LLC: TxDOT maintenance contract 100%+ complete, IH 30, Titus County ($7,756,806, 10 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Thk Construction LLC |
| Subcontractors | Hodges And Son Construction Company, INC. (1.76%); J. H. Oden Contracting Company (0.56%); Traffic Highway Maintenance, LLC (0.3%); Morris County Contractors, L.L.C. (0.35%); Cherokee Services (5.89%); 1 Priority Environmental Services, LLC (1.91%); Trp Construction Group, LLC (0.64%); True Roads Construction LLC (2.22%); Diamond Elite Barricades, LLC (1%); Texco Services, LLC (2.44%) |
| Progress | 104.29% complete, 76.06% of time used |
| Amount | $7,756,806 revised (original $3,819,729) |
| Change orders | $3,677,074 |
| Paid to date | $7,818,426 |
| Work | Maintenance |
| Location | IH 30, AT TANKERSLEY CREEK to ., Titus County, Atlanta District |
| Let / began | 2024-09-06 / 2024-11-25 |
| Latest estimate | 2026-10-02 |
| Contract number | 9243212 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.