# Thk Construction LLC: TxDOT bridge replacement contract 98% complete, FM 2610, Polk County ($2,475,737, 9 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Thk Construction LLC |
| Subcontractors | Hodges And Son Construction Company, INC. (12.75%); Diamond Elite Barricades, LLC (0.34%); Houston Sawing & Drilling (0.34%); Morris County Contractors, L.L.C. (1.62%); Toro Bravo Construction, LLC (0.09%); Cap River LLC (0.28%); True Roads, LLC (2.07%); Trp Construction Group, LLC (0.49%); R & G Construction, LLC (4.61%) |
| Progress | 98.4% complete, 105.71% of time used |
| Amount | $2,475,737 revised (original $2,472,737) |
| Paid to date | $2,433,181 |
| Work | Bridge Replacement |
| Location | FM 2610, FM 2610 to AT MENARD CREEK., Polk County, Lufkin District |
| Let / began | 2025-09-04 / 2025-12-16 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253019 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.