# Ti-Zack Concrete, LLC: TxDOT bridge widening or rehabilitation contract 30% complete, IH 27, Hale County ($3,816,554, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Ti-Zack Concrete, LLC |
| Subcontractors | Trumble Crane & Rigging (0.97%); Trp Construction Group, LLC (1.54%); Hydro Technologies, INC. (6.88%); One Way Concrete Construction, LLC (29.84%); A Brothers Milling, LLC (0.67%) |
| Progress | 30.24% complete, 61.28% of time used |
| Amount | $3,816,554 revised (original $3,773,614) |
| Change orders | $21,941 |
| Paid to date | $1,147,592 |
| Work | Bridge Widening Or Rehabilitation |
| Location | IH 27, IH 27 SB to AT FM 54, Hale County, Lubbock District |
| Let / began | 2024-06-05 / 2025-03-31 |
| Latest estimate | 2026-10-06 |
| Contract number | 6243020 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.