# Ti-Zack Concrete, LLC: TxDOT rehabilitation of existing road contract 79% complete, Various, Wharton County ($2,274,682, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Ti-Zack Concrete, LLC |
| Subcontractors | Ram-Rod Concrete Company, INC. (8.79%); Concrete Cutting & Breaking Company (0.87%); South Texas Traffic Alliance INC. (0.58%); Third Coast Services LLC (5.35%); Highway Barricades And Services, LLC (0.16%); Santa Fe Concrete Services LLC (2.92%); Robin Steel LLC (1.58%) |
| Progress | 79.48% complete, 73.42% of time used |
| Amount | $2,274,682 revised (original $2,130,273) |
| Change orders | $142,907 |
| Paid to date | $1,806,784 |
| Work | Rehabilitation Of Existing Road |
| Location | Various, FIRST ST/RAILROAD ST (ADJACENT TO S to MAIN ST/NORTH LIBERTY ST (ON BU 59S, Wharton County, Yoakum District |
| Let / began | 2025-06-05 / 2026-01-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 6253225 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.