# Ti-Zack Concrete, LLC: TxDOT maintenance contract 100% complete, Various, Lubbock County ($3,277,086, 3 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Ti-Zack Concrete, LLC |
| Subcontractors | One Way Concrete Construction, LLC (31.86%); Trp Construction Group, LLC (8.8%); Trumble Crane & Rigging (2.57%) |
| Progress | 99.78% complete, 83.89% of time used |
| Amount | $3,277,086 revised (original $2,795,872) |
| Change orders | $429,214 |
| Paid to date | $3,218,131 |
| Work | Maintenance |
| Location | Various, VARIOUS BRIDGES IN THE LUBBOCK DIST, Lubbock County, Lubbock District |
| Let / began | 2024-09-06 / 2024-12-16 |
| Latest estimate | 2026-10-06 |
| Contract number | 9243223 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.