# Traf-Tex, INC.: TxDOT miscellaneous construction contract 81% complete, IH 69, Montgomery County ($3,751,484)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Traf-Tex, INC. |
| Progress | 80.63% complete, 88.15% of time used |
| Amount | $3,751,484 revised (original $3,716,483) |
| Change orders | $35,001 |
| Paid to date | $3,024,955 |
| Work | Miscellaneous Construction |
| Location | IH 69, HARRIS COUNTY LINE to LIBERTY COUNTY LINE, Montgomery County, Houston District |
| Let / began | 2022-10-07 / 2025-03-07 |
| Latest estimate | 2026-09-30 |
| Contract number | 10223204 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.