# Traf-Tex, INC.: TxDOT corridor traffic management contract 100%+ complete, IH 69, Fort Bend County ($3,350,303)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Traf-Tex, INC. |
| Progress | 104.08% complete, 102% of time used |
| Amount | $3,350,303 revised (original $3,151,614) |
| Change orders | $125,687 |
| Paid to date | $3,410,964 |
| Work | Corridor Traffic Management |
| Location | IH 69, EAST OF SS 529 to SH 99, Fort Bend County, Houston District |
| Let / began | 2020-12-03 / 2023-11-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 12203204 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.