# Trevway, INC.: TxDOT bridge replacement contract 35% complete, CR, Fort Bend County ($1,852,857, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Trevway, INC. |
| Subcontractors | Ninos Rebar Construction LLC (0.72%); Durwood Greene Construction Co. (18.15%); Jh Contract Field Services, LLC (7.82%); Traffic Signs & Lines, LLC (0.71%); A1 Erosion Control (0.1%) |
| Progress | 35.15% complete, 38.1% of time used |
| Amount | $1,852,857 revised (original $1,818,854) |
| Paid to date | $639,380 |
| Work | Bridge Replacement |
| Location | CR, CR 234 (C MEYER RD) AT BEE CREEK to ., Fort Bend County, Houston District |
| Let / began | 2026-02-05 / 2026-07-06 |
| Latest estimate | 2026-09-30 |
| Contract number | 2263220 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.