# Trevway, INC.: TxDOT bridge replacement contract 60% complete, CR, Wharton County ($3,131,608, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Trevway, INC. |
| Subcontractors | Beaird Drilling Services, INC. (10.6%); Superior Traffic Control, LLC (0.49%); Sylva Construction, LLC (3.85%); Jh Contract Field Services, LLC (2.57%) |
| Progress | 60.42% complete, 57.14% of time used |
| Amount | $3,131,608 revised (original $3,100,106) |
| Paid to date | $1,872,958 |
| Work | Bridge Replacement |
| Location | CR, AT MUD CREEK to STR# AA04-18-001, Wharton County, Yoakum District |
| Let / began | 2025-03-04 / 2025-09-30 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253020 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.