# Trevway, INC.: TxDOT bridge replacement contract 63% complete, CR, Burleson County ($1,468,962, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Trevway, INC. |
| Subcontractors | Hemphill Wbe Pile Driving Co. (7.61%); Lonestar Traffic Safety, LLC (0.41%); Hodges And Son Construction Company, INC. (3.43%); Toro Bravo Construction, LLC (0.2%) |
| Progress | 63.13% complete, 80.33% of time used |
| Amount | $1,468,962 revised (original $1,449,786) |
| Change orders | $19,176 |
| Paid to date | $927,310 |
| Work | Bridge Replacement |
| Location | CR, ON CR 211 (LCR 211) to AT CEDAR CREEK TRIBUTARY, Burleson County, Bryan District |
| Let / began | 2022-04-07 / 2022-10-11 |
| Latest estimate | 2026-09-29 |
| Contract number | 4223217 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.