# Trevway, INC.: TxDOT bridge replacement contract 51% complete, CR, Wharton County ($2,648,292, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Trevway, INC. |
| Subcontractors | Sylva Construction Co. (3.45%); Skyline Bridge LLC (15.26%); Stripe Lines, INC. (0.64%); Sylva Construction, LLC (3.45%) |
| Progress | 50.95% complete, 34.7% of time used |
| Amount | $2,648,292 revised (original $2,614,789) |
| Paid to date | $1,332,194 |
| Work | Bridge Replacement |
| Location | CR, AT WILL CREEK #2 to STR# AA04-29-002, Wharton County, Yoakum District |
| Let / began | 2025-06-05 / 2026-02-09 |
| Latest estimate | 2026-10-05 |
| Contract number | 6253221 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.