# Tri State Electric, LTD.: TxDOT hazard elimination & safety contract 75% complete, IH 10, El Paso County ($6,231,003, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Tri State Electric, LTD. |
| Subcontractors | Organ Mountain Site Solutions LLC (4.99%); Apache Barricade & Sign (0.32%); Border Drilling LLC (2.1%); Apollo Constructors, INC. (8%); J-Ken Pipe & Steel, L.L.C. (0.03%) |
| Progress | 74.54% complete, 75.88% of time used |
| Amount | $6,231,003 revised (original $6,226,703) |
| Paid to date | $4,641,641 |
| Work | Hazard Elimination & Safety |
| Location | IH 10, REYNOLDS ST to US 62, El Paso County, El Paso District |
| Let / began | 2024-12-03 / 2025-09-02 |
| Latest estimate | 2026-10-02 |
| Contract number | 12243007 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.