# Tri State Electric, LTD.: TxDOT maintenance contract 80% complete, Various, El Paso County ($898,950, 1 sub)

**Score:** 25/100

| Field | Value |
|---|---|
| Prime contractor | Tri State Electric, LTD. |
| Subcontractors | Apache Barricade & Sign (1.04%) |
| Progress | 79.85% complete, 104% of time used |
| Amount | $898,950 revised (original $793,768) |
| Change orders | $75,182 |
| Paid to date | $693,881 |
| Work | Maintenance |
| Location | Various, DISTRICTWIDE, El Paso County, El Paso District |
| Let / began | 2024-02-02 / 2025-02-20 |
| Latest estimate | 2026-10-02 |
| Contract number | 2243235 |

## Why this score


Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.