# Tri State Electric, LTD.: TxDOT hazard elimination & safety contract 88% complete, BU 54A, El Paso County ($2,968,624, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Tri State Electric, LTD. |
| Subcontractors | 2h, LLC (2.15%); Border Drilling LLC (1.42%); Apache Barricade & Sign (0%); Synergy Project Contractors, INC. (3.99%) |
| Progress | 87.77% complete, 83.57% of time used |
| Amount | $2,968,624 revised (original $2,840,217) |
| Change orders | $126,907 |
| Paid to date | $2,604,297 |
| Work | Hazard Elimination & Safety |
| Location | BU 54A, 0.88 MI N OF SL 375 to 2.88 MI N OF SL 375, El Paso County, El Paso District |
| Let / began | 2023-04-05 / 2025-01-28 |
| Latest estimate | 2026-10-02 |
| Contract number | 4233218 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.