# Tri State Electric, LTD.: TxDOT hazard elimination & safety contract 100%+ complete, SH 20, El Paso County ($5,796,794, 4 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Tri State Electric, LTD. |
| Subcontractors | Hawk Construction (0.42%); Border Drilling LLC (0.42%); Del Mar Contracting, INC. (7.45%); Pmi Pavement Marking, LLC (6.65%) |
| Progress | 103.47% complete, 91.52% of time used |
| Amount | $5,796,794 revised (original $5,350,903) |
| Change orders | $340,891 |
| Paid to date | $5,889,519 |
| Work | Hazard Elimination & Safety |
| Location | SH 20, AT PA 2401/DONIPHAN DR/N MESA ST to ., El Paso County, El Paso District |
| Let / began | 2021-06-03 / 2023-10-23 |
| Latest estimate | 2026-10-02 |
| Contract number | 6213011 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.