# Tri State Electric, LTD.: TxDOT traffic protection devices contract 38% complete, Various, El Paso County ($8,626,137, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Tri State Electric, LTD. |
| Subcontractors | Border Drilling LLC (2.1%); Apache Barricade & Sign (2.83%) |
| Progress | 38.22% complete, 91% of time used |
| Amount | $8,626,137 revised (original $8,297,286) |
| Change orders | $168,851 |
| Paid to date | $3,236,166 |
| Work | Traffic Protection Devices |
| Location | Various, AT THE BRIDGE OF THE AMERICAS to ZARAGOZA PORT OF ENTRY, El Paso County, El Paso District |
| Let / began | 2022-09-07 / 2024-09-30 |
| Latest estimate | 2026-10-05 |
| Contract number | 9223040 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.