# Triple T Maintenance INC.: TxDOT maintenance contract 79% complete, US0180, Shackelford County ($289,809)

**Score:** 35/100

| Field | Value |
|---|---|
| Prime contractor | Triple T Maintenance INC. |
| Progress | 78.93% complete, 70.96% of time used |
| Amount | $289,809 revised (original $145,285) |
| Change orders | $145,284 |
| Paid to date | $229,338 |
| Work | Maintenance |
| Location | US0180, VARIOUS LOCATIONS IN to SHACKELFORD COUNTY, Shackelford County, Abilene District |
| Let / began | 2025-03-25 / 2025-05-19 |
| Latest estimate | 2026-10-02 |
| Contract number | 3250811 |

## Why this score
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.