# Trp Infrastructure Services, LLC: TxDOT overlay contract 81% complete, IH 10, Harris County ($1,651,464)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Trp Infrastructure Services, LLC |
| Progress | 81.41% complete, 171.43% of time used |
| Amount | $1,651,464 revised (original $1,682,562) |
| Paid to date | $1,369,745 |
| Work | Overlay |
| Location | IH 10, GESSNER to NORTH POST OAK, Harris County, Houston District |
| Let / began | 2025-12-03 / 2026-02-24 |
| Latest estimate | 2026-09-30 |
| Contract number | 12253211 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.