# True Roads Construction LLC: TxDOT rehabilitation of existing road contract 27% complete, US 82, Bowie County ($11,298,695, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | True Roads Construction LLC |
| Subcontractors | Marcoms Construction LLC (0.77%); Withers Construction, LLC (0.88%); Kiteco Property Solutions INC. (3.32%); Surface Preparation Technologies, LLC (0.15%); J. H. Oden Contracting Company (1.34%); Panola Sign & Barricade, INC. (0.6%); Striping Technology, L.P. (3.95%); Flex Supply, LLC (0.54%) |
| Progress | 26.74% complete, 20.19% of time used |
| Amount | $11,298,695 revised (original $10,382,445) |
| Change orders | $266,141 |
| Paid to date | $2,847,196 |
| Work | Rehabilitation Of Existing Road |
| Location | US 82, SH 8 to FM 1398, Bowie County, Atlanta District |
| Let / began | 2025-12-02 / 2026-05-17 |
| Latest estimate | 2026-10-01 |
| Contract number | 12253010 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.