# True Roads Construction LLC: TxDOT bridge replacement contract 99% complete, CR, Harrison County ($1,445,945, 4 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | True Roads Construction LLC |
| Subcontractors | Carthage Drilling, LLC (7.54%); J. H. Oden Contracting Company (1.79%); Morris County Contractors, L.L.C. (3.47%); Panola Sign & Barricade, INC. (1.08%) |
| Progress | 98.98% complete, 98.9% of time used |
| Amount | $1,445,945 revised (original $1,320,898) |
| Change orders | $100,218 |
| Paid to date | $1,406,598 |
| Work | Bridge Replacement |
| Location | CR, AT EIGHT MILE CREEK to ., Harrison County, Atlanta District |
| Let / began | 2025-06-04 |
| Latest estimate | 2026-10-02 |
| Contract number | 6253038 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.