# True Roads Construction LLC: TxDOT bridge replacement contract 96% complete, CR, Polk County ($1,656,086, 4 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | True Roads Construction LLC |
| Subcontractors | Flex Supply, LLC (1.03%); J. H. Oden Contracting Company (3.25%); Morris County Contractors, L.L.C. (3.01%); M & D Foundation Drilling Industries, INC. (8.7%) |
| Progress | 95.53% complete, 85.63% of time used |
| Amount | $1,656,086 revised (original $1,653,086) |
| Paid to date | $1,579,232 |
| Work | Bridge Replacement |
| Location | CR, AT LONG KING CREEK to ., Polk County, Lufkin District |
| Let / began | 2025-06-05 / 2026-01-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 6253228 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.