# Ttg Utilities, INC.: TxDOT rehabilitation of existing road contract 77% complete, FD, Coryell County ($5,787,023, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Ttg Utilities, INC. |
| Subcontractors | Bryant & Frey Construction Co. (2.15%); D. I. J. Construction, INC. (0.64%); Highway Traffic Control & Services, LLC (0.7%); Lone Star Paving Company (12.11%); Wolfe Construction Group, Incorporated (1.04%) |
| Progress | 77.21% complete, 82.22% of time used |
| Amount | $5,787,023 revised (original $4,647,464) |
| Change orders | $1,139,559 |
| Paid to date | $4,467,911 |
| Work | Rehabilitation Of Existing Road |
| Location | FD, CLEAR CREEK RD to WEST RANGE RD, Coryell County, Waco District |
| Let / began | 2025-06-04 / 2025-08-25 |
| Latest estimate | 2026-10-01 |
| Contract number | 6253037 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.