# Tucan Contracting, LLC: TxDOT bridge replacement contract 98% complete, CR, Navarro County ($1,246,365, 4 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Tucan Contracting, LLC |
| Subcontractors | Peachtree Construction, LTD. (8.5%); Toro Bravo Construction, LLC (0%); Wylie Drilling & Drainage, INC. (9.05%); Fortson Contracting, INC. (3.34%) |
| Progress | 98.11% complete, 52.28% of time used |
| Amount | $1,246,365 revised (original $1,223,665) |
| Paid to date | $1,200,499 |
| Work | Bridge Replacement |
| Location | CR, NW CR 4340 AT FROST BRANCH to ., Navarro County, Dallas District |
| Let / began | 2026-02-05 / 2026-04-15 |
| Latest estimate | 2026-10-05 |
| Contract number | 2263230 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.