# Urban Infraconstruction LLC: TxDOT widen non-freeway contract 19% complete, FM 549, Rockwall County ($30,009,684, 13 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Urban Infraconstruction LLC |
| Subcontractors | Straight Line Sawing & Sealing, INC. (0.29%); Wylie Drilling & Drainage, INC. (0.43%); Toro Bravo Construction, LLC (0%); Als. Trucking Service,LLC (2.8%); Act Saw Cutting & Removal (0.26%); Elite Striping, LLC (0.81%); Reynolds Asphalt & Construction Company (11.95%); Southern Cross Contractors, LLC (0.64%); Civil Tree Solutions, LLC (0.33%); Meade Servicing Group, INC. (0.39%); Texop Construction (0.51%); A.Z. Rebar Construction, INC. (0.55%); Mels Electric, LLC (0.6%) |
| Progress | 18.57% complete, 15.62% of time used |
| Amount | $30,009,684 revised (original $29,812,034) |
| Paid to date | $5,534,806 |
| Work | Widen Non-Freeway |
| Location | FM 549, SH 205 to SH 276, Rockwall County, Dallas District |
| Let / began | 2026-02-04 / 2026-05-04 |
| Latest estimate | 2026-10-02 |
| Contract number | 2263002 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.