# Vulcan Construction Materials, LLC: TxDOT materials-only contract 100%+ complete, US0181, Wilson County ($1,495,770)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Vulcan Construction Materials, LLC |
| Progress | 132.35% complete, 80.68% of time used |
| Amount | $1,495,770 revised (original $747,885) |
| Change orders | $747,885 |
| Paid to date | $1,979,644 |
| Work | Materials-Only Contract |
| Location | US0181, VARIOUS LOCATIONS THROUGHOUT FLORES to MAINTENANCE SECTION, Wilson County, San Antonio District |
| Let / began | 2025-01-28 / 2025-03-03 |
| Latest estimate | 2026-10-06 |
| Contract number | 1251511 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.