# Webber, LLC: TxDOT miscellaneous construction contract 100%+ complete, IH 35, Hays County ($86,633,817, 31 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Webber, LLC |
| Subcontractors | Rodd Frank Holdings LLC (0%); Calame Contracting, LLC (0.09%); Sk Concrete Services LLC (0.05%); Envirocon Systems INC. (0.09%); Sea2 Construction LLC (0.65%); Scott Derr Painting Co, LLC (0.22%); Curb Planet INC. (0.17%); Fibertel, LLC (0.27%); Beaver Contractors, LLC (0.07%); Cpave, INC. (0.03%); Cjw Construction Services, INC. (3.24%); Breda Company, INC. (0.01%); Cnd Contracting, LLC (0.16%); Hermanos Steel, LLC (0.35%); Adcock 4 Investments, LLC (3.52%); Highway Pavement Specialties, INC. (0.05%); Roadway Specialties, INC. (0.14%); Texas Environmental Management - San Antonio, INC. (0.59%); The Levy Company, INC. (10.8%); Trp Construction Group, LLC (0.8%); Wims Environmental Construction, LTD. (0.32%); Speedy Paving (0.47%); Eggemeyer Land Clearing, LLC (0.07%); Buyers Barricades San Antonio, LLC (0.36%); Lone Star Paving Company (10.94%); Toro Bravo Construction, LLC (0.03%); Aptus Group USA, LLC (0.27%); Keller North America, INC. (1.22%); B Comm Constructors L.L.C. (0.12%); National Works, INC. (0.02%); Frank Jr Reinforcement LLC (0.05%) |
| Progress | 103.44% complete, 99.55% of time used |
| Amount | $86,633,817 revised (original $81,218,267) |
| Change orders | $4,509,674 |
| Paid to date | $88,679,762 |
| Work | Miscellaneous Construction |
| Location | IH 35, SOUTH OF SH 80 to NORTH OF RM 12, Hays County, Austin District |
| Let / began | 2021-04-08 / 2021-08-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 4213201 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.